Fencing Works

Task / DescriptionSlow  Ave  Fast   Units
 Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 -   m/hr
 Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 -   no/hr
 Post Erection, Concrete, dig, erect, fix3.2 4.0 -   no/hr
 Fence Erection, Chainlink, posts at 1.5m-  4.2 -   m/hr
 Fence Erection, Chainlink, posts at 2.0m-  4.4 -   m/hr
 Fence Erection, Chainlink, posts at 3.0m-  5.5 -   m/hr
 Fence Erection, Chestnut Pailings, posts at 1.5m-  23.8 -   m/hr
 Fence Erection, Chestnut Pailings, posts at 2.0m-  33.3 -   m/hr
 Fence Erection, Chestnut Pailings, posts at 3.0m-  41.6 -   m/hr
 Fence Erection, Barbed Wire, posts at 1.5m-  71.4 -   m/hr
 Fence Erection, Barbed Wire, posts at 2.0m-  100.0 -   m/hr
 Fence Erection, Barbed Wire, posts at 3.0m-  125.0 -   m/hr
 Gate Erection, Chainlink on frame-  4.1 -   no/hr