Ground Excavation

Started by Technical Development ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Ground Excavation Rates (m3/hr):

Ground TypeBucketBulk WorksBasementsTrenchesSmall & Deep
Sand/Soil0.3m38.78.07.18.4>
 0.4m328.515.425.010.0
 0.5m350.020.028.613.3
Gravel0.3m37.16.96.14.5
 0.4m325.914.322.28.7
 0.5m340.018.128.611.1
Clay/Chalk0.3m37.16.56.14.1
 0.4m325.013.322.28.3
 0.5m340.016.728.610.5
V.Difficult0.3m36.15.95.44.1
 0.4m322.211.820.07.7
 0.5m328.611.820.06.7

Small or Deep Excavations

Task / DescriptionSlow  Ave  Fast   Units
 Hydraulic Excavator, 0.3m3 bucket, Sand/Soil6.7 8.4 9.9  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Gravel Beds3.2 4.5 5.0  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk3.3 4.1 5.2  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Hard Ground3.3 4.1 5.2  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Sand/Soil8.2 10.0 11.7  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Gravel Beds7.1 8.7 10.2  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk6.5 8.3 9.4  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Hard Ground6.3 7.7 9.1  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Sand/Soil12.2 13.3 15.4  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Gravel Beds10.2 11.1 12.9  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk9.7 10.5 12.1  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Hard Ground6.1 6.7 7.7  m3/hr