Escalator Installation
Modular Design Escalators PackagesThe escalator trusses are usually delivered in 1.6 m cubes, which include the internal workings etc. Normally 3 to 4 sections go to make up a standard escalator (an 11 m rise), however sizes and lengths vary greatly.Delivery Implications
- Last updated
- Updated
- Views
- 10 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Modular Design Escalators Packages
The escalator trusses are usually delivered in 1.6 m cubes, which include the internal workings etc. Normally 3 to 4 sections go to make up a standard escalator (an 11 m rise), however sizes and lengths vary greatly.
Delivery Implications
The largest single element is the nose piece which is approximately 1.8 m wide, 3 m long and 2.5 m high. This section weight 1,500 kg. The other truss sections weight only 1,000 kg at most. The maximum weight of an entire escalator (10 m rise) is estimated at 15,000 kg. It is usual to being the escalators in from the top landing and lower the whole truss down into its final position. Power supply being 415 volt 3 phase hard wired, T&C may be done with temporary supplies.
Typical Project Strategy
Sequence /timing of works:
- 16 wks = Develop concept design / submit for approval.
- 12 wks = Prepare preliminary design / submit for approval.
- 60 wks = Manufacture, test & site delivery, in conjunction with completion of final design.
- 4 wks = Initial delivery placing and connection of truss sections.
- 12-16 wks = Install escalators and commission.
- 12 wks = Test running of escalators.
- 12 wks = Trial running of escalators / System Operational.
Typical Escalator Installation Sequence Timing of single escalator:
- 1 wks = Assemble sections and truss position, align, level.
- 6 wks = Escalator contractor "stop work" period, to allow ABWF contractor to complete surrounding finishes.
- 5 wks = Final escalator installation, "Phase B" decking installation and glazing etc.
- 0 wks = Escalator Power-On required.
- 2 wks = Test performance "Phase C" prior to escalator Test Running.
- 2 wks = Full load test "Phase D" of escalator.
- 1 wks = Final test "Phase E"
- 1 wks = EMSD Inspection of installation.
- 1 wks = "Phase F" inspection.
Total installation time being 12 - 14 weeks, excluding the "Stop Work" period during which the civil finishing works are completed.
| Task / Description | Slow | Ave | Fast | Units |
| Truss type, Overall Installation (excl arch finishes) | 14.0 | 12.0 | 11.0 | wks |
| Truss type, Manufacture, test and deliver | - | 60.0 | 48.0 | wks |
| Truss type, Phase A assemble truss , position/level | - | 1.0 | - | wks |
| Truss type, Stop-Work for surrounding finishes | 8.0 | 6.0 | 4.0 | wks |
| Truss type, Phase B decking and glazing etc | - | 5.0 | - | wks |
| Truss type, Phase C performance testing | - | 2.0 | - | wks |
| Truss type, Phase D full load testing | - | 2.0 | - | wks |
| Truss type, Phase E final test and inspection | - | 2.0 | - | wks |