Rates, Norms & Durations

Hand Fill & Compact

Started by Technical Development ·
Last updated
Updated
Views
10 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Loose from side of excavation, including compaction (m3/hr)...
 

Material Ne 100m 100-200mm 200-300mm exc 300m
Loose Sand/Soil 0.85 1.02 1.28 1.69
Clay/Heavy Chalk 0.77 0.92 1.16 1.56
Hoging 0.81 0.97 1.20 1.61
Hardcode 0.71 0.84 1.06 1.41