Excavate & Load

Started by Technical Development ·
Last updated
Updated
Views
10 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Excavate Spoil Heaps and Load to Transport (m3/hr):

 

Material0.6 m30.8 m31.0 m31.2 m3
Sand/Soil20.025.630.335.7
Gravel20.425.631.337.0
Clay/Chalk18.523.227.833.3
Boulder Clay16.921.324.430.3

Note:

  • 0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity.
  • 20.0, 25.6, 30.3 and 35.7 etc are excavation rates in m3 / hr