Footing Reinforcement
ActivityTASKSTask - UOML - Barbender/Fitter (Mandays)L - Helper (Mandays)MMMFooting ReinforcementFoot Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor SteelMt0.28 Mandays/0.1Mt
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →
Activity | TASKS | Task - UOM | L - Barbender/Fitter (Mandays) | L - Helper (Mandays) | M | M | M |
Footing Reinforcement | Foot Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel | Mt | 0.28 Mandays/0.1Mt | 0.38 Mandays/0.1Mt | Bars - Include 5% Wastage | Binding Wire : 5 kg/0.1Mt | Cover Blocks - 10No/0.1Mt |
Foot Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel | Mt | 0.2 Mandays/0.1Mt | 0.28 Mandays/0.1Mt | Bars - Include 5% Wastage | |||
Foot Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel | Mt | 0.29 Mandays/0.1Mt | 0.32 Mandays/0.1Mt | Bars - Include 5% Wastage |
Comments
No comments yet.
Log in or join to comment