Hollorib Decking
In the Open Standard
Hollorib Decking Lay decking = 350 m2/day Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week) Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating
Started by Technical Development ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Hollorib Decking
Lay decking = 350 m2/day
Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week)
Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating