Manholes and Gulleys

Task / DescriptionSlow  Ave  Fast   Units
 Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm-  1.2 -   hrs/no
 Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm-  1.6 -   hrs/no
 Brickwork Manhole, 1.0 brick engineering-  0.3 -   m2/hr
 Brickwork Manhole, 1.5 brick engineering-  0.2 -   m2/hr
 Brickwork Manhole, 2.0 brick engineering-  0.2 -   m2/hr
 Benching to Manhole, under 0.5m2-  0.9 -   hrs/no
 Benching to Manhole, 0.5-0.75m2-  1.2 -   hrs/no
 Benching to Manhole, 0.75-1.0m2-  1.8 -   hrs/no
 Brickwork Manhole, build in pipes, under 150mm dia-  0.1 -   hrs/no
 Brickwork Manhole, build in pipes, 150-225mm dia-  0.2 -   hrs/no
 Brickwork Manhole, build in pipes, over 225mm dia-  0.3 -   hrs/no
 Brickwork Manhole, build in cast iron covers0.3 0.6 1.2  hrs/no
 Yard Gulleys, 75-150mm dia pipes, bed and level-  2.2 -   no/hr
 Yard Gulleys, 150-225mm dia pipes, bed and level-  1.8 -   no/hr
 Yard Gulleys, 225-300mm dia pipes, bed and level-  1.5 -   no/hr
 Road Gulleys, 600mm deep, bed and level-  1.2 -   no/hr
 Road Gulleys, 750mm deep, bed and level-  0.8 -   no/hr
 Road Gulleys, 900mm deep, bed and level-  0.4 -   no/hr
 Road Gulleys, 1,200mm deep, bed and level-  0.3 -   no/hr
 Road Gulleys, install gratings-  5.0 -   no/hr
 PVC Manhole-  15.0 -   mins/no

Land Drains

Task / DescriptionSlow  Ave  Fast   Units
 Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run-  11.6 -   m/hr
 Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run-  14.1 -   m/hr
 Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run-  18.8 -   m/hr
 Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run-  8.4 -   m/hr
 Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run-  10.2 -   m/hr
 Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run-  11.9 -   m/hr
 Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run-  5.4 -   m/hr
 Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run-  6.5 -   m/hr
 Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run-  7.9 -   m/hr

Drainage

Task / DescriptionSlow  Ave  Fast   Units
 PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run-  5.7 -   m/hr
 PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run-  8.1 -   m/hr
 PVC Drainage, 1m pipes, 100-150mm dia, over 30m run-  9.5 -   m/hr
 PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run-  12.2 -   m/hr
 PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run-  15.2 -   m/hr
 PVC Drainage, 3m pipes, 100-150mm dia, over 30m run-  18.2 -   m/hr
 PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run-  22.2 -   m/hr
 PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run-  27.7 -   m/hr
 PVC Drainage, 6m pipes, 100-150mm dia, over 30m run-  33.3 -   m/hr
 PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run-  10.6 -   m/hr
 PVC Drainage, 3m pipes, 150-200mm dia, over 30m run-  12.8 -   m/hr
 PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run-  21.2 -   m/hr
 PVC Drainage, 6m pipes, 150-200mm dia, over 30m run-  25.6 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run-  4.7 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run-  5.5 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run-  6.6 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run-  4.4 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run-  5.0 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run-  6.2 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run-  3.2 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run-  3.8 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run-  4.5 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run-  2.1 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run-  2.6 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run-  3.1 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run-  1.4 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run-  1.7 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run-  2.4 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run-  1.1 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run-  1.3 -   m/hr
 Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run-  1.6 -   m/hr
 Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run-  8.3 -   m/hr
 Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run-  10.0 -   m/hr
 Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run-  12.5 -   m/hr
 Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run-  7.7 -   m/hr
 Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run-  9.1 -   m/hr
 Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run-  10.0 -   m/hr
 Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run-  5.2 -   m/hr
 Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run-  6.2 -   m/hr
 Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run-  7.7 -   m/hr
 Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run-  2.7 -   m/hr
 Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run-  3.3 -   m/hr
 Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run-  4.0 -   m/hr
 Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run-  1.7 -   m/hr
 Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run-  2.1 -   m/hr
 Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run-  2.5 -   m/hr
 Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run-  1.4 -   m/hr
 Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run-  1.6 -   m/hr
 Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run-  2.1 -   m/hr
 PVC, Stoneware, Pitch Fibre & Concrete Joints-  2.4 -   mins/no
 Pitch Fibre Pipes, 75mm dia, 0-5m run-  9.1 -   m/hr
 Pitch Fibre Pipes, 75mm dia, 5-30m run-  16.6 -   m/hr
 Pitch Fibre Pipes, 75mm dia, over 30m run-  20.0 -   m/hr
 Pitch Fibre Pipes, 100mm dia, 0-5m run-  9.1 -   m/hr
 Pitch Fibre Pipes, 100mm dia, 5-30m run-  16.6 -   m/hr
 Pitch Fibre Pipes, 100mm dia, over 30m run-  20.0 -   m/hr
 Pitch Fibre Pipes, 150mm dia, 0-5m run-  6.6 -   m/hr
 Pitch Fibre Pipes, 150mm dia, 5-30m run-  12.5 -   m/hr
 Pitch Fibre Pipes, 150mm dia, over 30m run-  14.3 -   m/hr
 Pitch Fibre Pipes, 200mm dia, 0-5m run-  6.2 -   m/hr
 Pitch Fibre Pipes, 200mm dia, 5-30m run-  11.1 -   m/hr
 Pitch Fibre Pipes, 200mm dia, over 30m run-  12.5 -   m/hr
 Pitch Fibre Pipes, 225mm dia, 0-5m run-  5.8 -   m/hr
 Pitch Fibre Pipes, 225mm dia, 5-30m run-  10.0 -   m/hr
 Pitch Fibre Pipes, 225mm dia, over 30m run-  12.1 -   m/hr
 Hepsleve Rubber Joint System, 75mm dia, 0-5m run-  12.5 -   m/hr
 Hepsleve Rubber Joint System, 75mm dia, 5-30m run-  14.3 -   m/hr
 Hepsleve Rubber Joint System, 75mm dia, over 30m run11.2 16.6 30.1  m/hr
 Hepsleve Rubber Joint System, 100mm dia, 0-5m run-  10.0 -   m/hr
 Hepsleve Rubber Joint System, 100mm dia, 5-30m run-  12.5 -   m/hr
 Hepsleve Rubber Joint System, 100mm dia, over 30m run-  14.3 -   m/hr
 Hepsleve Rubber Joint System, 150mm dia, 0-5m run-  7.1 -   m/hr
 Hepsleve Rubber Joint System, 150mm dia, 5-30m run-  9.1 -   m/hr
 Hepsleve Rubber Joint System, 150mm dia, over 30m run8.3 10.0 13.8  m/hr
 Hepsleve Rubber Joint System, 225mm dia, 0-5m run-  6.8 -   m/hr
 Hepsleve Rubber Joint System, 225mm dia, 5-30m run-  4.5 -   m/hr
 Hepsleve Rubber Joint System, 225mm dia, over 30m run-  5.5 -   m/hr
 Hepsleve Rubber Joint System, 300mm dia, 0-5m run-  2.5 -   m/hr
 Hepsleve Rubber Joint System, 300mm dia, 5-30m run-  2.9 -   m/hr
 Hepsleve Rubber Joint System, 300mm dia, over 30m run-  3.7 -   m/hr
 Hepsleve Rubber Joint System, over 375mm dia, 0-5m run-  1.9 -   m/hr
 Hepsleve Rubber Joint System, over 375mm dia, 5-30m run-  2.3 -   m/hr
 Hepsleve Rubber Joint System, over 375mm dia, over 30m run-  2.7 -   m/hr
 Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run-  2.8 -   m/hr
 Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run-  3.4 -   m/hr
 Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run-  3.8 -   m/hr
 Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run-  2.7 -   m/hr
 Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run-  3.2 -   m/hr
 Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run-  3.6 -   m/hr
 Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run-  2.5 -   m/hr
 Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run-  2.9 -   m/hr
 Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run-  3.4 -   m/hr
 Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run-  2.4 -   m/hr
 Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run-  2.7 -   m/hr
 Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run-  3.3 -   m/hr
 Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run-  2.2 -   m/hr
 Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run-  2.6 -   m/hr
 Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run-  2.9 -   m/hr
 Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run-  1.1 -   m/hr
 Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run-  2.4 -   m/hr
 Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run-  2.5 -   m/hr
 Concrete Pipes, 1.5m pipes, 1,050mm dia-  2.9 4.2  m/day
 Concrete Pipes, 1.5m pipes, 1,500mm dia-  2.5 3.8  m/day
 Concrete Pipes, 1.5m pipes, 1,800mm dia-  2.1 2.6  m/day
 Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run-  3.6 -   m/hr
 Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run-  4.3 -   m/hr
 Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run-  5.0 8.0  m/hr
 Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run-  3.4 -   m/hr
 Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run-  4.1 -   m/hr
 Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run-  4.5 9.0  m/hr
 Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run-  3.3 -   m/hr
 Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run-  3.8 -   m/hr
 Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run-  4.1 -   m/hr
 Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run-  3.0 -   m/hr
 Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run-  3.5 -   m/hr
 Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run-  4.0 -   m/hr
 Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run-  2.8 -   m/hr
 Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run-  3.3 -   m/hr
 Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run-  3.7 -   m/hr
 Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run-  2.6 -   m/hr
 Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run-  3.1 -   m/hr
 Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run-  3.6 -   m/hr
 Lay Shingle Around Pipework, under 150mm dia-  7.0 -   m/hr
 Lay Shingle Around Pipework, over 150mm dia4.0 5.5 9.0  m/hr