Building & Construction Production Middle East Rates & Build Times:

Started by Technical Development ·
Last updated
Updated
Views
20 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Building & Construction Production Middle East Rates & Build Times:

In this chapter

  1. 01Blockwork
  2. 02Building Frameworks
  3. 03Computer Room / Raised Floors
  4. 04Concrete Related Works
  5. 05Decking
  6. 06Demolition & Break Out
  7. 07Drainage, Manholes and Gulleys
  8. 08Earthworks & Excavation
  9. 09Fencing Works
  10. 10Foundation Works
  11. 11Granolithic Flooring
  12. 12Mosaic Tiles
  13. 13Partitioning
  14. 14Preparation Works
  15. 15Roofs & Waterproofing
  16. 16Sand / Cement Floor Screeding
  17. 17Terrazzo Flooring
  18. 18Tower Cranes
  19. 19Wet Trade Finishes
  20. 20Wood Block Flooring
  21. 21Working Platforms

22 comments

Oldest first
  1. Faraz Memon ·

    Hi friends,

    Greetings :)

    I am in need of above files in excel or pdf format as i am working on a vast project having buildings and infra-structure all together and i am having difficulty with the productivity rate. I'll be really grateful if someone could send me the files on following email : faraz_memon85@yahoo.com.

    Thanks & Best Regards

  2. Mark McErlean ·

    Good afternoon,

    This is an excellent facility & website. I am wondering if there is an Excel version of rates is available to send to me? My email address is conorbob88@gmail.com. I would of course be extreamly greatful.

    Regards,

    Conor

  3. Ashley Jones ·

    Hi there, 

     

    Sending this information to ajones@logikal.co.uk in excel format would be greatly appreciated. 

     

    Thanks, 

  4. Ashley Jones ·

    Hi there, 

     

    Sending this information to ajones@logikal.co.uk in excel format would be greatly appreciated. 

     

    Thanks, 

  5. Ahmed Hammad ·
    Kindly send me this excellent productivity rates in Excel format on civil_eng_ahmedhammad@yahoo.com
  6. Josh Dures ·

    Hello! 

     

    Can someone send me a copy of construction rates in excel format to jdd89@hotmail.co.uk

  7. Babatope Lewis ·

    Good afternoon,

    This is an excellent and informative facility & website. I am wondering if there is an Excel version of rates is available to send to me flow2baba@gmail.com I would be extreamly greatful.

    Regards,

    Lewis

  8. Ahmed Abouelnaga ·

    Could i have acopy of production in excel format 

    Eng.ahmedabouelnaga@hotmail.com

  9. Anthony Agner ·

    Dear,

    could you send to my email a copy - anthonyagner@yahoo.com

    Thanks!

  10. Alvin Amponin ·

    kindly please send me copy in excel sheet at amponin.alvin@yahoo.com

     

    Thanks a lot.

  11. Negar Somi ·

    Hi there, 

     

    Sending "Building & Construction Production Rates & Build Times" to nsomie2000@yahoo.com  in excel format would be greatly appreciated. 

     

    Kindest Regards

  12. Maher Alrawashdeh ·

    Good afternoon,

    This is an excellent facility & website. I am wondering if there is an Excel version of rates is available to send to me? My email address is maher.rawashdeh@gmail.com. I would of course be extreamly greatful.

    Regards,

    Maher

  13. Wael Sobhy ·

     Please if there is an Excel version of rates is available to send to me

    wael.sobhy.alex@gmail.com 

    I would be extreamly greatful.

    Regards,

  14. Mohammed Abuzar ·

    Hi,

     

    I am looking for standars Labor Productivity and rates in Excel , Can you please share me to this email id abuzar86@gmail.com

  15. Omar Ababneh ·

    Dear All, 

     

    Could you please provicde me with an excel sheet clarifying labor productivity, specially duct fabrication, installation and insulation, in Middle East ? 

    Could you please email it to Omarwababneh@gmail.com 

    Thanks in Advance, 

    Omar 

  16. Barrie Mackenzie ·

    Hi,

    Could i have an excel version of building durations please - bmackenzie78@gmail.com

  17. admin ·

    Hello,

    We do not have a spreadsheet or PDf to share as we are trying to make this a collaborative database for people to share online.

    However, I will ask the team at the next meeting what we can do to help with this request.

    If anyone has any rates to offer we'd love to talk to them.

    Regards... PP Admin Team.

  18. Dominic Planner ·

    Can I be sent an Excel or PDF version of these rates please?

     

      Thanks

  19. Mohamed Osama ·

    I am looking for standars Labor Productivity and rates in Excel , Can you please share me to this email 

    mohamedosamaattiah@gmail.com

     

  20. Noel Talo ·
    Hi there, Sending "Building & MEP Constructional Production Rates & Build Times" to ngtalo@yahoo.com in excel format would be greatly appreciated. Kindest Regards
  21. Muhammad Saqib ·

     Hello Everyone,

    I need productivity rates of manpower in building construction. 

    I am fresher planning engineer and recently joined in a company. Now i have to plan a project of high rise building.

    So please somebody send me the material related to buidling construction which helps me in making a good planning and scheduling.

     

    Thanks

     

    Email: saqib.bhatti92@gmail.com

  22. Ramon Dizon ·

    Good day PP community,

    I am currently working on a resource loading task for a building structure.

    I would like to request a productivity rate for the installation of hollow core slab with corresponding equipment and manpower.

    Thanks for sharing and keep on planning!

     

    Regards,

     

    Ramon Dizon

     

     