Soft Landscaping
In the Open Standard
SoilSpread topsoil, prepare for turf/seeding = 2.5 m2/hr Spread fertilizer and rake in = 25.0 m2/hrPlantingHedges or Shrubs, ne 750 mm high = 4.0 no/hr Hedges or Shrubs, exc 750 m high = 1.5 no/hr Saplings, ne 3.0 m high = 1.7 hrs/noTurfingTypical rate including minor preparations = 135 m2/dayLandsc
Started by Technical Development ·
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Soil
Spread topsoil, prepare for turf/seeding = 2.5 m2/hr Spread fertilizer and rake in = 25.0 m2/hr
Planting
Hedges or Shrubs, ne 750 mm high = 4.0 no/hr Hedges or Shrubs, exc 750 m high = 1.5 no/hr Saplings, ne 3.0 m high = 1.7 hrs/no
Turfing
Typical rate including minor preparations = 135 m2/day
Landscaping
| Task / Description | Slow | Ave | Fast | Units |
| Top Soil, spread, level and prepare for turf or seeding | - | 2.5 | - | m2/hr |
| Top Soil, rake in fertilizer for seeding | - | 25.0 | - | m2/hr |
| Planting, Shrubs and Hedges, under 750mm high | - | 4.0 | - | no/hr |
| Planting, Shrubs and Hedges, over 750mm high | - | 1.5 | - | no/hr |
| Planting, Saplings, under 3.0m high | - | 1.7 | - | no/hr |
| Turfing, including for minor preparations | - | 16.8 | - | m2/hr |