Ramp formwork

ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Ramp formworkRamp - Shuttering & Providing SupportSqm0.22 Mandays/Sqm

Started by admin ·
Last updated
Updated
Views
13 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

 

Activity

TASKS

Task - UOM

Labor (L) - Carpenter (Mandays)

Labor (L) - Helper (Mandays)

Material (M)

Material (M)

Material (M)

Ramp formwork

Ramp - Shuttering & Providing Support

Sqm

0.22 Mandays/Sqm

0.44 Mandays/Sqm

MS Floor Form Panel - 750 x 600 - 13.3Nos/10Sqm

MS Floor Form Panel - 1250 x 500 : 6.4Nos/10Sqm

Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm and Shuttering Oil : 5Ltr/10Sqm

Ramp - Deshuttering & Stacking Appropriately at Same Location

Sqm

0.13 Mandays/Sqm

0.26 Mandays/Sqm

    