Plastering

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Plastering

Task / DescriptionSlow  Ave  Fast   Units
 Browning (undercoat), Internal Walls under 2.5m high2.2 2.8 3.1  m2/hr
 Browning (undercoat), Internal Walls over 2.5m high2.1 2.6 2.8  m2/hr
 Browning (undercoat), Reveals and Columns less than 100mm wide9.9 10.0 10.1  m2/hr
 Browning (undercoat), Reveals and Columns 100-200mm wide5.2 5.4 6.4  m2/hr
 Browning (undercoat), Reveals and Columns 200-300mm wide3.3 3.6 3.9  m2/hr
 Covings-  5.0 -   m/hr
 Skimming (topcoat), Internal Walls under 2.5m high6.1 6.7 7.3  m2/hr
 Skimming (topcoat), Internal Walls over 2.5m high5.5 6.1 6.7  m2/hr
 Skimming (topcoat), Reveals and Columns less than 100mm wide12.6 13.8 15.4  m2/hr
 Skimming (topcoat), Reveals and Columns 100-200mm wide7.7 8.3 9.8  m2/hr
 Skimming (topcoat), Reveals and Columns 200-300mm wide4.5 5.0 5.5  m2/hr
 Plaster Board to Ceilings3.2 4.5 5.5  m2/hr
 Plastering Ceilings, 1 Bonding, 1 Skimming1.1 1.7 2.4  m2/hr
 Plastering Ceilings, Topcoat Skimming2.7 3.2 5.4  m2/hr