| Task / Description | Slow | Ave | Fast | Units |
| Concrete Slabs, laid on bedding, to slight falls | 2.7 | - | 4.2 | m2/hr |
| Concrete Slabs, laid on bedding, to steep falls | 2.3 | - | 2.7 | m2/hr |
| Concrete Slabs, laid in mortar, to slight falls | 1.5 | - | 2.3 | m2/hr |
| Concrete Slabs, laid in mortar, to steep falls | 1.1 | - | 1.5 | m2/hr |
| Concrete Slabs, laid on sand, to slight falls | 1.7 | - | 2.8 | m2/hr |
| Concrete Slabs, laid on sand, to steep falls | 1.6 | - | 1.9 | m2/hr |
| Cobble Stones, laid in mortar, no patterns | - | 0.3 | - | m2/hr |
| Cobble Stones, laid in mortar, with patterns | - | 0.2 | - | m2/hr |
| Artificial Stone, laid on sand, with patterns | - | 2.5 | - | m2/hr |
| Brick Paviors, in mortar, straight joints | 0.9 | 1.3 | 1.9 | m2/hr |
| Brick Paviors, in mortar, herringbone pattern | - | 1.0 | 1.2 | m2/hr |
| Gravel Paths, including preparation of sub-base | - | 10.5 | - | m2/hr |
| Concrete Paths, 100mm thick, including preparation of sub-base | - | 2.5 | - | m2/hr |
| Concrete Kerbs or Channels, laid straight | - | 6.2 | - | m/hr |
| Concrete Kerbs or Channels, laid to 5m radius | - | 4.5 | - | m/hr |
| Concrete Kerbs or Channels, laid to 10m radius | - | 5.0 | - | m/hr |
| Concrete Kerbs or Channels, laid to 20m radius | - | 5.5 | - | m/hr |
| Stone/Granite Kerbs or Channels, laid straight | - | 3.5 | - | m/hr |
| Concrete Edging, laid straight | - | 7.7 | - | m/hr |
| Concrete Edging, laid to 5m radius | - | 5.8 | - | m/hr |
| Concrete Edging, laid to 10m radius | - | 6.2 | - | m/hr |
| Concrete Edging, laid to 20m radius | - | 7.1 | - | m/hr |
| Cutting and Fitting Ends, Concrete Kerbs | - | 6.6 | - | no/hr |
| Cutting and Fitting Ends, Channels | - | 5.8 | - | no/hr |
| Cutting and Fitting Ends, Concrete Edging | - | 8.3 | - | no/hr |