Skip to content
Rates, Norms & Durations

Place Concrete

Barrowing Concrete (m3/hr).Receive concrete from mixer/lorry direct to barrow, wheel to placing position, tip and return.

Started by admin ·
Last updated
Updated
Views
9 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Barrowing Concrete (m3/hr).

Receive concrete from mixer/lorry direct to barrow, wheel to placing position, tip and return.

Distance
0 - 10 m
2.32
 
10 - 20 m
1.81
 
20 - 50 m
1.08
As above but including load concrete from deck/tray.
                
Distance
0 - 10 m
0.99
 
10 - 20 m
0.87
 
20 - 50 m
0.66
Extra over to place direct, for dump and shovel in from side, a typical rate of 0.26 hrs/m3.
Direct From Ready Mix Lorry (m3/hr).
 
Type
Ready Mix
Via Dumper
Via Dumper
 
Tip Direct
Tip Direct
Thrown In
Mass Fill
3.12
2.56
1.49
50mm Blinding
1.27
1.06
0.82
Ground Beams ne 0.1 m2 SA
1.52
1.30
1.00
Ground Beams ex 0.1 m2 SA
1.69
1.49
1.16
Pile Caps ne 0.1 m2 SA
1.16
1.06
0.79
Pile Caps ex 0.1 m2 SA
2.56
2.13
7.69
Duct Walls
0.78
0.71
0.52
Stub Columns
0.43
0.39
0.29
Ground Slab ne 155 mm
2.13
1.82
1.22
Ground Slab 150-300 mm
2.33
1.96
1.27
Ground Slab 300-500 mm
2.56
2.13
1.35
Drains, Bed & Cover
0.91
0.85
0.73
By Lorry Mounted Concrete Pump (m3/hr).
 
 
Thickness -->
13.5 m3/hr
18 m3/hr
 
 
 
 
Solid Slabs
ne 100 mm
2.17
2.63
 
100 - 150 mm
2.44
2.94
 
150 - 200 mm
2.63
3.23
 
200 - 300 mm
2.86
3.45
 
300 - 500 mm
3.23
3.85
Coffered Slabs
 
1.64
1.82
Columns
0.5 - 0.10 m2
1.59
1.59
 
exc 0.10 m2
1.82
1.82
Wall
ne 150 mm
1.61
1.89
 
150 - 225 mm
1.89
2.33
 
exc 225 mm
2.56
3.23
Independent Beams
 
1.54
1.54
Stairs and Landings
 
1.27
1.89
 
By Dumper, From Ready Mix Lorry To Position (m3/hr).
             
Dumper Capacity -->
0.6 m3
0.8 m3
1.2 m3
1.5 m3
2.3 m3
0 - 20 m
10.41
14.08
18.82
25.00
33.33
20 - 50 m
 9.09
12.36
16.39
22.22
29.41
50 - 100 m
 7.29
10.41
13.88
18.86
25.00
100 - 250 m
 5.78
 7.87
10.00
13.51
18.18
250 - 500 m
 3.65
 4.95
 8.33
 8.95
12.35
500 - 750 m
 2.16
 2.92
 4.27
 5.43
 7.87
750 - 1,000 m
 -
 -
 -
 3.97
 5.78
 By Tower/Mobile Crane (m3/hr).
                                                      
 
 
0.4 m Skip
0.6 m Skip
0.8 m Skip
Pile Caps
SA ne 2 m2
1.19
1.39
1.61
Mass Fill Pours
SA 2-5 m3
1.75
2.04
2.33
 
ne 10 m3
3.70
4.17
4.76
 
10-25 m3
4.00
4.55
0.84
 
exc 25 m3
4.35
5.00
5.86
Slabs
ne 100 mm
0.90
1.09
1.21
 
100-150 mm
1.09
1.31
1.47
 
150-200 mm
1.26
1.53
1.69
 
200-300 mm
1.26
1.53
1.69
 
Exc 300 mm
1.38
1.66
1.85
Trough & Coffered Slabs
 
0.95
1.09
1.21
Structural Topping ne 100 mm
 
0.90
1.09
1.25
Stairs & Landings
 
0.64
0.64
0.64
Blinding
ne 150 mm
0.88
1.00
1.10
Beams
SA 0-0.05 m
0.52
0.58
0.69
 
SA 0.05-0.1 m
0.58
0.65
0.78
 
SA ex 0.1 m
0.76
0.85
1.02
Walls
ne 100 mm
0.64
0.76
0.88
 
100-150 mm
0.76
0.92
1.05
 
150-300 mm
0.95
1.11
1.28
 
exc 300 mm
1.10
1.28
1.47
Columns
SA ne 0.05 m2
0.43
0.45
0.48
 
SA 0.05-0.1 m2
0.48
0.50
0.54
 
SA ex 0.1 m2
0.51
0.53
0.57

Concrete Placement

Task / DescriptionSlow  Ave  Fast   Units
 Placing concrete, lorry based pump30.0 40.0 50.0  m3/hr
 Hollorib Decking, concrete topping85.0 100.0 120.0  m2/hr
 Hollorib Decking, concrete topping, incl PowerFloat40.0 50.0 70.0  m2/hr
 Placing Concrete, By Wheelbarrow over 1-10m2.1 2.3 2.5  m3/hr
 Placing Concrete, By Wheelbarrow over 10-20m1.5 1.8 2.1  m3/hr
 Placing Concrete, By Wheelbarrow over 20-50m0.8 1.1 1.5  m3/hr
 Placing Direct From Readymix Lorry, Mass Fill2.8 3.1 3.3  m3/hr
 Placing Direct From Readymix Lorry, 50mm Blinding-  1.3 1.6  m3/hr
 Placing Direct From Readymix Lorry, Ground Beams1.5 -  1.7  m3/hr
 Placing Direct From Readymix Lorry, Pile Caps1.0 1.5 2.3  m3/hr
 Placing Direct From Readymix Lorry, Duct Walls-  0.8 1.1  m3/hr
 Placing Direct From Readymix Lorry, Stub Columns-  0.4 0.6  m3/hr
 Placing Direct From Readymix Lorry, Ground Slab2.1 2.3 2.6  m3/hr
 Placing Direct From Readymix Lorry,Drains Bed and Cover-  0.9 1.0  m3/hr
 Placing From Tower Crane, Pile Caps1.2 1.4 1.6  m3/hr
 Placing From Tower Crane, Mass Fill4.0 4.5 5.5  m3/hr
 Placing From Tower Crane, Slabs under 150mm thick0.9 1.3 1.7  m3/hr
 Placing From Tower Crane, Slabs over 150mm thick1.2 1.5 1.8  m3/hr
 Placing From Tower Crane, Trough/Coffered Slabs0.9 1.1 1.2  m3/hr
 Placing From Tower Crane, Stairs and Landings0.6 0.7 0.9  m3/hr
 Placing From Tower Crane, Blinding0.8 1.0 1.1  m3/hr
 Placing From Tower Crane, Beams under 150mm thick0.5 0.6 0.8  m3/hr
 Placing From Tower Crane, Beams over 150mm thick0.6 0.8 1.0  m3/hr
 Placing From Tower Crane, Walls0.6 1.1 1.5  m3/hr
 Placing From Tower Crane, Columns0.4 0.5 0.6  m3/hr

Comments

No comments yet.

Log in or join to comment