Rates, Norms & Durations
Painting & Decorations
In the Open Standard
Started by Oliver Melling ·
- Last updated
- Updated
- Views
- 10 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Painting
| Task / Description | Slow | Ave | Fast | Units |
| Prepare Walls | - | 14.2 | - | m2/hr |
| Prepare Doors | - | 12.5 | - | m2/hr |
| Prepare Door Frames | - | 25.0 | - | m/hr |
| Burn Off / Heat Strip Paintwork | - | 1.1 | - | m2/hr |
| Internal Timber, 1 coat primer before fixing, generally | - | 6.7 | - | m2/hr |
| Internal Timber, 1 coat primer before fixing, timber lengths | - | 20.0 | - | m/hr |
| Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss | - | 1.7 | 2.1 | m2/hr |
| Internal Timber, touchup primer, 1 undercoat, 1 coat gloss | - | 3.1 | 3.8 | m2/hr |
| Internal Timber, polyurethane varnish, 2 coats | - | 3.3 | - | m2/hr |
| Internal Timber, polyurethane varnish, 3 coats | - | 2.2 | - | m2/hr |
| Internal Timber, linseed oil to hardwood, 2 coats | - | 3.6 | - | m2/hr |
| External Timber, windows and frames | - | 2.4 | - | m2/hr |
| External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, | - | 1.5 | - | m2/hr |
| External Timber, touchup primer, 2 undercoats, 1 coat gloss, | - | 2.0 | - | m2/hr |
| External Timber, 2 coats wood preservative | - | 4.0 | - | m2/hr |
| External Timber, 3 coats polyurethane varnish | - | 2.0 | - | m2/hr |
| Internal Walls, 2 coats emulsion to plaster | - | 8.0 | - | m2/hr |
| Internal Walls, 2 coats emulsion to brick/blockwork | - | 6.0 | - | m2/hr |
| Internal Walls, 1 mist, 2 coats emulsion to plaster | - | 6.0 | - | m2/hr |
| Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork | - | 4.5 | - | m2/hr |
| Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster | - | 2.3 | - | m2/hr |
| Internal Walls, undercoat to door frame | - | 20.0 | - | m/hr |
| Internal Walls, gloss to door frame | - | 16.5 | - | m/hr |
| Internal Walls, undercoat to door | - | 7.1 | - | m2/hr |
| Internal Walls, gloss to door | - | 6.2 | - | m2/hr |
| External Walls, 2 coats sandtex to render/concrete | - | 2.5 | - | m2/hr |
| External Walls, 2 coats sandtex to brick/blockwork | - | 2.0 | - | m2/hr |
| External Walls, 1 sealer, 2 emulsion to render/concrete | - | 2.0 | - | m2/hr |
| External Walls, 1 sealer, 2 emulsion to brick/blockwork | - | 1.7 | - | m2/hr |
| Floors, epoxy paint | - | 2.9 | - | m2/hr |
| Ceilings, emulsion paint, 2 coats | - | 6.1 | - | m2/hr |
| Ceilings, emulsion paint, 3 coats | - | 5.0 | - | m2/hr |
| Ceilings, textured paint | - | 4.2 | - | m2/hr |
| Ceilings, artex finish | - | 4.1 | - | m2/hr |
| Internal Steelwork, 1 primer, 1 undercoat, 1 gloss | 1.3 | 2.4 | - | m2/hr |
| External Steelwork, 1 primer, 2 undercoats, 1 gloss | 0.9 | 1.7 | - | m2/hr |
| Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss | - | 2.5 | - | m/hr |