Staircase formwork
ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Staircase formworkStaircase (Excluding Spiral Staircase) - Shuttering & Providing SupportSqm
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Activity | TASKS | Task - UOM | Labor (L) - Carpenter (Mandays) | Labor (L) - Helper (Mandays) | Material (M) | Material (M) | Material (M) |
Staircase formwork | Staircase (Excluding Spiral Staircase) - Shuttering & Providing Support | Sqm | 0.23 Mandays/Sqm | 0.46 Mandays/Sqm | MS Floor Form Panel - 750 x 600 - 2.2Nos/Sqm | Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm | Shuttering Oil : 5Ltr/10Sqm |
Staircase (Excluding Spiral Staircase) - Deshuttering & Stacking Appropriately at Same Location | Sqm | 0.14 Mandays/Sqm | 0.28 Mandays/Sqm |