Walls formwork

ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Walls formworkWalls (Any Thickness), Including Buttresses - Shuttering & Providing Support - Up to 3.5m Height

Started by admin ·
Last updated
Updated
Views
9 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

 

Activity

TASKS

Task - UOM

Labor (L) - Carpenter (Mandays)

Labor (L) - Helper (Mandays)

Material (M)

Material (M)

Material (M)

Walls formwork

Walls (Any Thickness), Including Buttresses - Shuttering & Providing Support - Up to 3.5m Height

Sqm

2.22 Mandays/10Sqm(Including Both Sides)

2.64 Mandays/10Sqm(Including Both Sides)

MS Wall Form Panel - 1250 x 500 - 32 Nos/10Sqm(Including Both Sides)

Props - 2m to 3m Long : 4Nos/Rm(Including Both Sides)

Shuttering Oil : 5Ltr/10Sqm(On One Side)

 

Walls - Deshuttering & insitu Stacking

Sqm

1.32 Mandays/10Sqm(Including Both Sides)

1.76 Mandays/10Sqm(Including Both Sides)

   