Wall & Ceiling Coverings

Paper CoveringsWall paper and lining paper = 5.00 m2/hr Vinyl and washable papers = 4.20 m2/hrCeiling lining paper = 4.00 m2/hrRates in relation to one skilled craftsman and labourer.Wallpapering...

Started by Technical Development ·
Last updated
Updated
Views
10 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Paper Coverings

Wall paper and lining paper = 5.00 m2/hr Vinyl and washable papers = 4.20 m2/hr

Ceiling lining paper = 4.00 m2/hr

Rates in relation to one skilled craftsman and labourer.

Wallpapering...

Task / DescriptionSlow  Ave  Fast   Units
 Strip Existing Wallpaper (3 layers) & Prepare Walls-  5.0 -   m2/hr
 Fix Wallpaper and lining paper-  5.0 -   m2/hr
 Fix Vinyl and Washable paper-  4.2 -   m2/hr
 Fix Ceiling Lining Paper-  4.0 -   m2/hr
Wall Finishes...
Task / DescriptionSlow  Ave  Fast   Units
 Mosaic Tiling, 0.045x0.045m-  1.1 1.5  no/hr
 Clay, quarry Tiles, Window Cills, setout and level-  55.5 -   m/hr
 Clay, quarry Tiles, Window Cills, fix, grout and clean-  1.5 -   m2/hr
 Ceramic Tiles 150x150mm, Ledges/Upstands20.4 27.1 32.0  no/hr
 Ceramic Tiles 150x150mm, Areas under 1.5m2 per room0.9 1.0 1.2  m2/hr
 Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room1.4 1.6 1.9  m2/hr
 Ceramic Tiles 150x150mm, Areas over 2.5m2 per room1.5 1.7 2.1  m2/hr
 Ceramic Tiles 150x150mm, Extra Over for Cutting-  41.6 -   no/hr
 Ceramic Tiles 108x108mm, Ledges/Upstands-  62.5 -   no/hr
 Ceramic Tiles 108x108mm, Areas under 1.5m2 per room1.0 1.3 1.5  m2/hr
 Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room1.6 1.8 2.1  m2/hr
 Ceramic Tiles 108x108mm, Areas over 2.5m2 per room1.7 1.9 2.2  m2/hr
 Ceramic Tiles 108x108mm, Extra Over for Cutting-  125.0 -   no/hr
 Ceramic Tiles, Grouting Works2.2 2.5 2.6  m2/hr