Spread and Level
Task / DescriptionSlow  Ave  Fast   Units
 Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile13.9 20.4 25.0  m3/hr
 Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile7.6 9.5 12.6  m3/hr
 Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile14.2 20.4 25.6  m3/hr
 Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile7.6 10.2 12.8  m3/hr
 Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile12.7 18.4 23.2  m3/hr
 Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile6.9 8.9 11.6  m3/hr
 Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile11.6 16.9 21.3  m3/hr
 Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile6.3 8.2 10.4  m3/hr
 Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile23.8 28.5 35.7  m3/hr
 Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile16.7 18.5 20.4  m3/hr
 Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile25.0 32.0 37.0  m3/hr
 Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile17.2 19.3 21.2  m3/hr
 Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile21.7 27.5 33.3  m3/hr
 Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile15.1 16.9 18.8  m3/hr
 Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile19.6 24.5 30.3  m3/hr
 Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile13.7 15.9 17.5  m3/hr
 Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil18.6 28.5 38.5  m3/hr
 Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil24.4 37.2 50.0  m3/hr
 Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel18.9 28.6 38.4  m3/hr
 Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel24.2 37.2 50.0  m3/hr
 Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore15.8 23.5 31.2  m3/hr
 Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore19.2 29.6 40.0  m3/hr
 Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay17.2 26.4 35.7  m3/hr
 Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay22.2 33.8 45.4  m3/hr
 Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil43.5 48.0 52.6  m3/hr
 Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil55.5 61.1 66.7  m3/hr
 Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel43.8 48.3 52.9  m3/hr
 Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel55.5 61.1 66.7  m3/hr
 Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore37.1 40.3 43.5  m3/hr
 Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore47.6 51.6 55.6  m3/hr
 Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay43.8 45.7 47.6  m3/hr
 Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay55.6 59.1 62.5  m3/hr