Walls Reinforcement

ActivityTASKSTask - UOML - Barbender/Fitter (Mandays)L - Helper (Mandays)MMMWalls ReinforcementWalls Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor SteelMt0.41 Mandays/0.1Mt

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

 

Activity

TASKS

Task - UOM

L - Barbender/Fitter (Mandays)

L - Helper (Mandays)

M

M

M

Walls Reinforcement

Walls Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel

Mt

0.41 Mandays/0.1Mt

0.45 Mandays/0.1Mt

Bars - Include 5% Wastage

Binding Wire : 5 kg/0.1Mt

Cover Blocks - 10No/0.1Mt

 

Walls Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars - Include 5% Wastage

  
 

Walls Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.39 Mandays/0.1Mt

0.43 Mandays/0.1Mt

Bars - Include 5% Wastage

  
 

Walls Rein - Stirrups Cutting and Bending

Mt

0.47 Mandays/0.1Mt

0.5 Mandays/0.1Mt

Bars - Include 5% Wastage

  
 

Walls Rein - Stirrups Teing

Mt

0.55 Mandays/0.1Mt

0.57 Mandays/0.1Mt

Bars - Include 5% Wastage

  