Shades Formwork

ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Shades FormworkWeather Shade, Chajjas, Corbels Shuttering (Including Propping)Sqm

Started by admin ·
Last updated
Updated
Views
7 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

 

Activity

TASKS

Task - UOM

Labor (L) - Carpenter (Mandays)

Labor (L) - Helper (Mandays)

Material (M)

Material (M)

Material (M)

Shades Formwork

Weather Shade, Chajjas, Corbels Shuttering (Including Propping)

Sqm

0.12 Mandays/Sqm

0.14 Mandays/Sqm

MS Floor Form Panel - 750 x 600 - 2.2Nos/Sqm

Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm

Shuttering Oil : 0.3Ltr/Sqm

Weather Shade, Chajjas, Corbels - Deshuttering & Stacking Appropriately at Same Location

Sqm

0.07 Mandays/Sqm

0.08 Mandays/Sqm

    