Rates, Norms & Durations
Screeding
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 7 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Screeding...
| Task / Description | Slow | Ave | Fast | Units |
| Sand/Cement Floor Screed, 15-20mm thick | - | 4.8 | 5.7 | m2/hr |
| Sand/Cement Floor Screed, 20-30mm thick | - | 4.6 | 5.5 | m2/hr |
| Sand/Cement Floor Screed, 30-40mm thick | 3.2 | 4.2 | 5.3 | m2/hr |
| Sand/Cement Floor Screed, 40-50mm thick | 2.0 | 3.8 | 5.2 | m2/hr |
| Sand/Cement Floor Screed, 50-65mm thick | - | 3.3 | 3.9 | m2/hr |
| Sand/Cement Floor Screed, 65-100mm thick | - | 3.0 | 3.6 | m2/hr |
| Fix/Setout Screed Battens | - | 10.0 | - | m/hr |