Restoration Works

Task / DescriptionSlow  Ave  Fast   Units
 Façade Cleaning, Water Jetting-  25.0 -   m2/day
 Façade Cleaning, Acid Etching-  9.0 -   m2/day
 Façade Cleaning, Grit Blasting-  12.0 -   m2/day
 Cladding Restoration, Brickwork-  6.5 -   m2/day
 Cladding Restoration, Stonework courses-  20.0 -   m/day