Road Markings
In the Open Standard
Road and Car Park Markings 75 mm road lines = 20.5 m/hr Road writing = 3.5 hrs/word or symbol
Started by Technical Development ·
- Last updated
- Updated
- Views
- 10 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Road and Car Park Markings
- 75 mm road lines = 20.5 m/hr
- Road writing = 3.5 hrs/word or symbol
1 comment
Oldest firstWhats the expected productivity for 100 mm wide strip ?