Rates, Norms & Durations
Waffle Flooring
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 11 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Rate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr). Conservative Erection Rate...
- 2.4 m grid, ne 3.5 m high soffit = 1.42 m2/hr
- 3.5 - 5.5 m high soffit = 1.13 m2.hr
Typical composite rate of 18.5 m2/day per 4 man gang. Rate includes decking, waffles and reinforcement fixing.