Removable Ground Anchors

Started by Technical Development ·
Last updated
Updated
Views
9 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Removable Ground Anchors Recent innovation of "removable" ground anchor system. Steel cables are doubles up and threaded over a roller at the anchor end. Once de-stressed, they can be pulled out. 1 rig can achieve...

  • Drill 30 m shaft 7.0 hrs
  • Install strands/setup anchor 6.0 hrs
  • Grout in strands 2.0 hrs
  • Stressing can be done 4 - 7 days after grouting.

Usually at 3 m horizontal centres and can only be worked on with 5 - 6 m spacings. So a hit and miss method must be adopted, giving a significant programme constraint.