Fitout & Finishes

Started by Technical Development ·
Last updated
Updated
Views
9 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →
Fitout & Finishes Rates & Build Times:

In this chapter

  1. 01Carpentry & Joinery
  2. 02Carpentry Carcassing
  3. 03Carpentry Final Fixing
  4. 04Ceiling Finishes
  5. 05Facade Waterproofing
  6. 06Floor Finishes
  7. 07Kitchen Installations
  8. 08Painting & Decorations
  9. 09Rendering
  10. 10Restoration Works
  11. 11Soft Landscaping
  12. 12Stone Cladding
  13. 13Wall & Ceiling Coverings

1 comment

Oldest first
  1. Rowstone Fausto ·

     

    Wood Doors and Frames    
    Door Frames and Trim    
    Single Exterior  ea3mh/unit
    Double Exterior ea6mh/unit
    Single Interior  ea3mh/unit
    Double Interior  ea4mh/unit
    Sliding Door Frame  ea4mh/unit
         
    Doors, Fit, Hand, and Lock    
    Single Exterior  ea5mh/unit
    Double Exterior  ea8mh/unit
    Single Interior  ea5mh/unit
    Double Interior  ea7mh/unit
    Screen Doors  ea2mh/unit
         
    Metal Doors    
    Single  ea6mh/unit
    Double  ea9mh/unit
         
    Miscellaneous Doors Complete with Trim and Hardware    
    Rolling, Manual Operated  ea29mh/unit
    Rolling, Motor Operated  ea36mh/unit
    Sliding, Manual Operated  ea20mh/unit
    Sliding, Motor Operated  ea26mh/unit
    Sliding, Fire  ea19mh/unit
         
    Garage Doors    
    Wood 16' X 7'  ea8mh/unit
    Aluminum 16' X 7'  ea10mh/unit
    Scuttles  ea10mh/unit
    Caulking  ft0.005mh/unit
         
    NOTES:     
    1. Includes jambs, stops, casings, and weather stripping.   
    2. Does not include sills or thresholds.    
    3. On wood doors, if power planes, hinge butt routers, and lock mortisers are used, use 0.75 multiplier on installation time.
         
    Window Installation    
    Work Element Description Unit Man-Hours Per Unit    
         
    Wood Windows    
    Double Hung  ea4mh/unit
    Casement, Single  ea4mh/unit
    Fixed, Wood Sash  ea3mh/unit
    Jalouse  ea2mh/unit
    Skylights  ea8mh/unit
         
    Metal Windows Casement     
    Commercial Projected  ea2mh/unit
    Skylights  ea2mh/unit
    Double Hung  ea9mh/unit
    Louvers ea5mh/unit
    Screens  ea2mh/unit
    Venetian Blinds  ea2mh/unit
    Weatherstripping  ea3mh/unit
    Caulking  ft0.003 
         
    SUGGESTED CREW SIZE: Two to six BUs    
    NOTES:     
    1. Installation includes drilling for fasteners, expansion shields, installing plugs, toggle bolts, blocking, hinges, locks, and other hardware.
    2. For special panic device for doors add three hours for single, four hours for double doors.
         
    Glass and Glazing    
    Work Element Description Unit Man-Hours Per Unit    
         
    Small Panels 2-FT. Square or Less  ft0.2mh/unit
    0.19 sg.m.- m21.7 
    Medium Panels 2- to 6-FT Square  ft0.2mh/unit
    0.0185-to 0.557 sq.m. m21.8 
    Large Panels 6- to 10-FT Square  ft0.2mh/unit
    0.557- to 1.0 sq.m. m22.3 
    Plate Glass Store Fronts 200- to 400- FT Square  ft21.0mh/unit
    18- to 37 sq.m. m2226.1 
         
    NOTES:     
    1. Estimates are based on putty set installation: if installed with metal stops and rubber, double the
    man-hour figures; if vinyl set, snap-on triple man-hour figures; for insulated glass use 0.67 multiplier
    2. When glazing from outside using scaffolding or swinging staging, one man is required on the ground
    to support two glaziers; use 1.5 multiplier    
    3. For winter work add use 1.25 multiplier.    
    4. Do not air ship insulated glass units such as Thermopane, Twindow, etc., due to unequal
    pressurization.    