Rates, Norms & Durations
Reinforcement Ratios
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Reinforcement Ratios
| Task / Description | Slow | Ave | Fast | Units |
| Pile Cap, Concrete m3 x Ratio = Rebar Tonnes | - | 14.8 | - | % ratio |
| Base Slab, Concrete m3 x Ratio = Rebar Tonnes | - | 13.2 | 14.1 | % ratio |
| Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes | - | 20.6 | 25.6 | % ratio |
| Platform Slab, Concrete m3 x Ratio = Rebar Tonnes | - | 15.6 | - | % ratio |
| Columns, Concrete m3 x Ratio = Rebar Tonnes | 15.8 | 18.7 | 28.7 | % ratio |
| Walls, Concrete m3 x Ratio = Rebar Tonnes | 14.7 | 15.0 | - | % ratio |