OFC Laying

OFC LayingBy Using Concrete/Road Cutter EquipmentResourcesSurvey Team of 4 (1 Suveyor , 3 Assistants)Equipment with Operator and HelperCutting Line Marking team ( 2-3 Persons)OFC cable laying team ( 4 Persons)Splicing team (2 technicians )Productivityif everything is planned properly with adequate o

Started by Praphulla Chaudhari ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

OFC Laying

By Using Concrete/Road Cutter Equipment

Resources

  • Survey Team of 4  (1 Suveyor , 3 Assistants)
  • Equipment with Operator and Helper
  • Cutting Line Marking team ( 2-3 Persons)
  • OFC cable laying team ( 4 Persons)
  • Splicing team (2  technicians )

Productivity

if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be  achieved.

By using trenching machine

  • Equipment with Operator and helper
  • Mini Dozer with operator
  • OFC Laying laying team (6-8 persons)
  • Rest resources as per above

Productivity

If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.