This page is part of the Rates, Norms & Durations library.
Open the norms tables →Mesh reinforcement - to slabs = 10.5 m2/hr
Mesh reinformcement - to beams/columns = 2.5 m2/hr
Reinforcement
| Task / Description | Slow | Ave | Fast | Units |
| Slabs/Foundations, steelfixing, 6mm | 40.3 | 38.4 | 36.5 | hrs/tonne |
| Slabs/Foundations, steelfixing, 8mm | 28.2 | 26.9 | 25.8 | hrs/tonne |
| Slabs/Foundations, steelfixing, 10mm | 22.5 | 20.6 | 20.1 | hrs/tonne |
| Slabs/Foundations, steelfixing, 12mm | 16.9 | 16.3 | 15.4 | hrs/tonne |
| Slabs/Foundations, steelfixing, 16mm | 12.0 | 11.5 | 10.9 | hrs/tonne |
| Slabs/Foundations, steelfixing, 20mm | 9.2 | 8.6 | 8.2 | hrs/tonne |
| Slabs/Foundations, steelfixing, 25mm | 6.9 | 6.7 | 6.5 | hrs/tonne |
| Slabs/Foundations, steelfixing, 32mm | 5.7 | 5.5 | 5.2 | hrs/tonne |
| Slabs/Foundations, steelfixing, 40mm | 5.3 | 5.1 | 4.9 | hrs/tonne |
| Slabs/Foundations, steelfixing, 50mm | 5.2 | 4.9 | 4.6 | hrs/tonne |
| Beams/Columns, steelfixing, 6mm | 55.4 | 52.8 | 50.6 | hrs/tonne |
| Beams/Columns, steelfixing, 8mm | 38.8 | 37.0 | 35.1 | hrs/tonne |
| Beams/Columns, steelfixing, 10mm | 29.5 | 28.4 | 26.9 | hrs/tonne |
| Beams/Columns, steelfixing, 12mm | 23.4 | 22.4 | 21.9 | hrs/tonne |
| Beams/Columns, steelfixing, 16mm | 16.6 | 15.8 | 15.1 | hrs/tonne |
| Beams/Columns, steelfixing, 20mm | 12.4 | 11.9 | 11.3 | hrs/tonne |
| Beams/Columns, steelfixing, 25mm | 9.9 | 9.2 | 8.7 | hrs/tonne |
| Beams/Columns, steelfixing, 32mm | 6.8 | 6.6 | 6.2 | hrs/tonne |
| Beams/Columns, steelfixing, 40mm | 6.1 | 5.9 | 5.6 | hrs/tonne |
| Beams/Columns, steelfixing, 50mm | 6.1 | 5.9 | 5.6 | hrs/tonne |
| Walls, steelfixing, 6mm | 41.2 | 40.8 | 39.1 | hrs/tonne |
| Walls, steelfixing, 8mm | 29.2 | 28.6 | 27.4 | hrs/tonne |
| Walls, steelfixing, 10mm | 22.7 | 22.0 | 21.2 | hrs/tonne |
| Walls, steelfixing, 12mm | 17.6 | 17.3 | 16.9 | hrs/tonne |
| Walls, steelfixing, 16mm | 12.4 | 12.2 | 11.8 | hrs/tonne |
| Walls, steelfixing, 20mm | 9.4 | 9.2 | 8.7 | hrs/tonne |
| Walls, steelfixing, 25mm | 7.4 | 7.2 | 7.0 | hrs/tonne |
| Walls, steelfixing, 32mm | 7.0 | 6.8 | 6.4 | hrs/tonne |
| Walls, steelfixing, 40mm | 6.4 | 6.1 | 5.9 | hrs/tonne |
| Walls, steelfixing, 50mm | 5.3 | 5.1 | 4.8 | hrs/tonne |
| Staircases, steelfixing, 6mm | 48.9 | 48.0 | 45.5 | hrs/tonne |
| Staircases, steelfixing, 8mm | 34.4 | 33.6 | 31.9 | hrs/tonne |
| Staircases, steelfixing, 10mm | 26.6 | 25.8 | 24.3 | hrs/tonne |
| Staircases, steelfixing, 12mm | 20.9 | 20.4 | 19.5 | hrs/tonne |
| Staircases, steelfixing, 16mm | 14.6 | 14.4 | 13.8 | hrs/tonne |
| Staircases, steelfixing, 20mm | 11.3 | 10.8 | 10.5 | hrs/tonne |
| Staircases, steelfixing, 25mm | 8.6 | 8.4 | 8.2 | hrs/tonne |