Strutting
In the Open Standard
Strutting To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable. To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable. To remove these struts, allow a rate of 3.5 days per strut.
Started by Technical Development ·
- Last updated
- Updated
- Views
- 7 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Strutting
To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable.
To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable.
To remove these struts, allow a rate of 3.5 days per strut.