Strutting

Strutting To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable. To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable. To remove these struts, allow a rate of 3.5 days per strut.

Started by Technical Development ·
Last updated
Updated
Views
7 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Strutting

To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable.

To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable.

To remove these struts, allow a rate of 3.5 days per strut.