Initial Works

Clearing Site of Bushes, shrubs, roots25.00 m2/hr
Lifting turf to be sorted and stacked  2.95 m2/hr

 Cutting Down Trees & Roots

Small Trees / Shrubs14 hrs/each
600 mm - 900 mm Girth18 hrs/each
900 mm - 1,200 mm Girth22 hrs/each
1,200 - 1,500 mm Girth26 hrs/each

Cutting Down Hedges & Roots

Hawthorn- 1.0 m high0.9 m/hr
 - 1.5 m high0.8 m/hr
 - 2.0 m high0.6 m/hr

Site Clearance

Task / DescriptionSlow  Ave  Fast   Units
 Shrubs and Bushes, dig up and removal-  25.0 38.0  m2/hr
 Turf, lifting and removal-  2.9 -   m2/hr
 Trees, small sizes and shrubs-  14.0 -   m2/hr
 Trees and Shrubs, 500mm - 900mm girth-  18.0 -   hrs/no
 Trees and Shrubs, 900mm - 1200mm girth-  22.0 -   hrs/no
 Trees and Shrubs, 1200mm - 1500mm girth-  26.0 -   hrs/no
 Hedges and Roots, 0.5-1.0m high-  0.9 -   m/hr
 Hedges and Roots, 1.0-1.5m high-  0.8 -   m/hr
 Hedges and Roots, 1.5-2.0m high-  0.6 -   m/hr